Fallago Rig WIND FARM

What's happening?

Activity Date Detail
Main works - Construction commencement 7th November 2011 Milestone
Progress - February 2012 5th March 2012 Community
Progress - April 2012 Apr 2012 Community
Electrical installation works commence 21st May 2012 Milestone
Progress - June 2012 Jun 2012 Community
Foundations - Over 80% installed 14th June 2012 Milestone
Progress - July 2012 Jul 2012 Community
1st turbine component delivery 9th July 2012 Milestone
Progress - September 2012 Sep 2012 Community
All Turbine Foundations Complete 17th September 2012 Milestone
400/33kV Transformers Installed 21st September 2012 Milestone
50% of Turbines Erected 26th October 2012 Milestone
Progress - November 2012 Nov 2012 Community
400kV System Energised 11th January 2013 Milestone
Site 33kV Infrastructure Energised to first Wind Turbine Generator 24th January 2013 Milestone
Final Turbine Erected 9th February 2013 Milestone
Site Deliveries 27th March 2013 Community
Fallago Rig Site Location

Fallago Rig Site Location

Site Inspections

Site Inspections

Home - The Wind Farm - What's happening? - Community - Studies - Milestones - Picture gallery - Contact us - Have your say - Search - Terms, Conditions & Disclaimer

Copyright © 2014 - Wind Prospect Ltd

Content Management System and Database Design BristolContent Management System and Database Design Bristol